San Diego Children’s Hospital DEGS of San Diego, Inc.
Project Highlights
- Built, operates and maintains hospital cogeneration central plant, nearly doubling hospital’s electric generating capacity
- Installed 3.5-megawatt natural gas-fired combustion turbine
- Installed absorption chillers to provide 1,320 tons of cooling capacity
- Installed two natural gas-fired boilers and a heat recovery steam generator with the capacity to supply 45 million btu/hr of hot water.
Overview
Duke Energy Generation Services (DEGS) entered into a 15-year agreement with Children's Hospital and Health Center to build and operate a cogeneration central plant for its hospital in San Diego, Calif. Under the agreement, DEGS replaced the existing 23-year-old cogeneration plant with a new central plant as well as installed boilers and chillers for hot water and air conditioning. The central plant nearly doubled the hospital’s electric generating capacity.
- View complete project sheet (32 KB pdf)